From brief to lit in 29 days

Typical bulletin-scale build. Spectaculars run 45–60. Permits and engineering run in parallel, not in sequence, which is where the time comes from.

Day 0

Brief + site survey

We measure the actual site, not the map. Sight lines, approach speed, ambient light, what blocks it at 6 p.m.

Day 3

Engineering

Load calc, wind rating to ASCE 7, motor and blower spec, electrical draw against the available service.

Day 7

Stamped drawings

Fabrication set and structural set, sealed by a PE licensed in the state the board stands in.

Day 10

Permit + landlord

Municipal sign permit, electrical permit, landlord and media-owner sign-off filed together, not in sequence.

Day 21

Fabrication

Steel, skin, motion and lighting built and dry-fitted in the shop. You get photos of the assembled unit before it ships.

Day 28

Install

Night crane window, 4–6 hours, lane closure permit in hand. Crew is site-badged.

Day 29

Live + monitored

Board goes on. Remote monitoring starts the same night, with a named engineer on the account.