02 — Process

From brief to lit in 29 days

Typical bulletin-scale build. Spectaculars run 45–60. Permits and engineering run in parallel, not in sequence, which is where the time comes from.

Day 0

Brief + site survey

We measure the actual site, not the map. Sight lines, approach speed, ambient light, what blocks it at 6 p.m.

Day 3

Engineering

Load calc, wind rating to ASCE 7, motor and blower spec, electrical draw against the available service.

Day 7

Stamped drawings

Fabrication set and structural set, sealed by a PE licensed in the state the board stands in.

Day 10

Permit + landlord

Municipal sign permit, electrical permit, landlord and media-owner sign-off filed together, not in sequence.

Day 21

Fabrication

Steel, skin, motion and lighting built and dry-fitted in the shop. You get photos of the assembled unit before it ships.

Day 28

Install

Night crane window, 4–6 hours, lane closure permit in hand. Crew is OSHA 30 and site-badged.

Day 29

Live + monitored

Board goes on. Remote monitoring starts the same night, with a named engineer on the account.